A. General standards. The following standards shall apply to all shipping containers in the Town of Windham:
(1) Housing of land uses. Shipping containers shall not be used to conduct land use activities that are carried on in a principal building or an accessory building;
(2) Stacking. Shipping containers shall not be stacked one on top of the other;
(3) Floor area. The floor area of a shipping container shall be measured by calculating the footprint of the container from its exterior walls;
(4) Location. Shipping containers shall not be located in any of the following areas:
(a) Parking spaces required by this chapter.
(b) Required front, side, or rear yard areas (see
Article 4: Zoning Districts).
(c) A location that reduces vehicular sight distance below minimum Maine Department of Transportation standards.
(d) A location that would cause a hazard to the traveling public.
(e) A location that impacts stormwater runoff.
B. Residential district standards.
(1) No more than one shipping container shall be allowed on any lot.
(2) Permit required. A permit shall be required for the installation of a shipping container in all residential zoning districts.
(3) Time limit. A shipping container shall not be located on-site for more than six months, with the exception that one extension of not more than three months may be granted at the discretion of the Code Enforcement Officer.
(4) Permitted shipping containers. A shipping container shall only be permitted for the temporary storage of residential items under the following circumstances:
(a) While a resident is in the process of moving into or out of a home;
(b) While a home is being remodeled; or
(c) After a home or building has experienced a fire, flood, or other damaging event.
(5) Permitted items. Items such as, but not limited to, the following shall be permitted in a shipping container:
(a) Household furniture;
(b) Appliances;
(c) Bathroom fixtures;
(d) Clothing; and
(e) Building materials.
C. Nonresidential district standards. The following standards shall apply to Shipping Containers that are currently located, or proposed, in a nonresidential district:
(1) The total floor area of all shipping containers on site shall not exceed 700 square feet. Additional shipping containers that exceed the 700 square feet limitation shall not be allowed by variance.
(2) If the property on which the shipping container is located received a site plan approval on or after March 13, 1991, the Planning Board shall be responsible for review and approval under the following standards:
(a) Conditional use.
(b) Site plan review.
(3) The shipping container must come into compliance with this chapter by March 21, 2001, unless good cause can be shown by the petitioner. After March 21, 2001, any existing shipping containers shall be removed from the site, unless:
(a) There is a pending conditional use application before the Board of Appeals.
(b) There is a pending conditional use and site plan application before the Planning Board.
(4) Shipping containers that are part of an existing commercial or industrial use, and are being actively used for the temporary storage and eventual shipping of goods, products, or materials that are manufactured or assembled as part of the commercial or industrial use, shall be allowed, provided that:
(a) The location of the shipping containers is duly noted on the site plan if the project was reviewed by the Planning Board and/or the Board of Appeals, or the building permit plot plan if no Planning Board or Board of Appeals review was required.
(b) The same shipping container(s) shall not be located on site for more than 30 consecutive days at a time.
D. Construction project standards.
(1) Shipping containers may be placed on property where a construction project is occurring. The shipping container shall only be utilized for the storage of construction materials, equipment, tools, etc.
(2) A permit shall not be required from the Code Enforcement Officer, Planning Board, and/or Board of Appeals.
(3) The shipping container(s) shall be removed within 30 days after the completion of the construction project.